Multipurpose Facility / new curling facility update
As
you hopefully have heard by now the official sod turning took place recently
for the Multipurpose facility. Following are the next steps prior to major
construction activity this spring.
·
Detailed design
and cost updates for all 4 components will be presented to City Council in
November / December. Location is in the SE quadrant of the City; generally speaking East of
WalMart, North of the Casino and West of the fair grounds. Look for the sign at
the intersection of Carlton Trail and Heritage Way.
·
Council will call
for construction tenders for 4 components in January / February. The go ahead
to award construction tenders for 2 to 4 components will be based upon tendered
cost estimates and money raised / committed to the project.
·
The first two
components in the queue will be the aquatic centre and performing arts
facility; these go first due to the way federal and provincial grants for the
project are structured.
·
There is a
strong likelihood that the curling facility will be part of the first phase of
construction with a good opportunity to see all four components (aquatic,
performing arts, curling and fieldhouse) constructed at one time.
·
There are
details such as facility governance, management, lease agreements, etc. that
remain to be worked out over the next 12 months.
·
Monies raised
and/or committed to mid-November total over $29 million with major
contributions coming from the City ($10 million plus $1 million from Provincial
gas tax), Provincial and Federal governments ($7 million each), Battlefords
Tribal Council ($2.75 million), Dekker Familiy / Rawlco Radio ($1
million), Granite Curling Club
($500 thousand) and RM of North Battleford ($125 thousand).
·
Expect to see
a major fundraising campaign and announcements roll out early in the New Year.
|